Installation site and infrastructure
The installation site must meet the following conditions prior to installation:
- The surface on which the system components are installed must be level and sturdy.
- The minimum load-bearing capacity of the floor must be 150 % of the total weight.
- The installation location must be chosen so that the system components are not positioned on an edge, drain channel or similar surface.
- The system is not approved for use in danger zones.
Before installing the system, please note the additional requirements regarding the installation site and infrastructure, which are included in the Technical data.